6. Multiple Inverter Support


This section outlines optional tests for communications software clients that intend to manage multiple downstream inverters. A subset of the test procedure must be repeated with a multiple inverter test setup to validate a communication software client’s capability to support multiple downstream devices. Multiple inverter support will be flagged against the communication software client CEC listing.


Compliance to these tests will be validated during a witnessing for the Export Limitation Test Procedure.


6.1 Electrical Test Setup

Multiple inverter support tests will require an electrical test setup as shown in the diagram and table below:


Component

Additional requirement

Inverters (minimum 2)

Configured to receive commands from a communications software client (native, gateway or cloud). Both inverters to be

below the same common metering point

Inverter meter

Measures or enables calculation of net

export

DC source

PV panels or DC Supply of at least 2kW DC

per inverter during test execution

Load

At least 500W of switchable load

Component

Additional requirement

Inverters (minimum 2)

Configured to receive commands from a communications software client (native, gateway or cloud). Both inverters to be

below the same common metering point

Inverter meter

Measures or enables calculation of net

export

DC source

PV panels or DC Supply of at least 2kW DC

per inverter during test execution

Load

At least 500W of switchable load

Diagram  Description automatically generated

Component

Additional requirement

Inverters (minimum 2)

Configured to receive commands from a communications software client (native, gateway or cloud). Both inverters to be

below the same common metering point

Inverter meter

Measures or enables calculation of net

export

DC source

PV panels or DC Supply of at least 2kW DC

per inverter during test execution

Load

At least 500W of switchable load


Figure 7 – Example Electrical Test Setup for Multiple Inverter Support


The party undertaking the test is responsible for ensuring such a test setup is available during test execution.


6.2 In-Scope Tests


The following tests must repeated with multiple inverters present to achieve certification for multiple inverter support.


• 5.1 Monitoring

o 5.1.1 Validate Measurements

• 5.2 Control

o 5.2.1 Export Limit Control

o 5.2.2 Load Following

o 5.2.3 Default Control Fallback